Maximizing Productivity with PARASPIN

Case Study


The project manager estimated that using traditional methods, the pulls would require four men working eight hours. PARASPIN helped complete the job with a three-man crew in three hours. This resulted in a labor savings of $1,265, a 72 percent decrease from traditional estimates. Project margin was further maximized by cutting to circuit length with cable measuring counters that eliminated all scrap.


  • Electrical construction company


  • Pull six circuits of 750 MCM tray rated XHHW cable at a waste water facility


  • PARASPIN reels, cut to circuit length, just-in-time delivery, layering, Installed pulling eyes


  • Completed on time

  • Labor reduced over 72 percent

  • No scrap created